MRP logic : Planned delivary time .

73 Views

Hi all ,

i have query in MRP :

I have FG and ROH in bom , i have requirement of FG for this mnth end 31.03.2008 for 100 kg , Time required to convert ROh to FG is 5 days . So when i am doing the Backward scheduling the system is calculating the start date as 26.03.2008 .But for ROH plan delivary time is 60 days , the system is rescheduling te date as 26.03.2008,, why can't the system schedules after 60 days when ROH will be available .

Pl guide for the same