no schedule lines due

Former Member
0 Kudos

Hi SAP Gurus,

I am getting error message when creating delivery for an order.

Error : No schedule lines due for delivery upto the selected date.

Please advise

Naveen

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

please check Delivery selection date (VL01 screen)

If you also enter a sales order number, the system checks the delivery

selection date against each schedule line for each item. If either the

material availability date or the transportation planning date falls on

or before the delivery selection date, the system copies the item into

the delivery.

goto your sales order (VA03), double click on item(s) and check Schedule Lines - have a look at

Deliv.date

Answers (2)

Answers (2)

former_member184555
Active Contributor
0 Kudos

Hi

The prerequisites for creating a delivery are ,

1. Atleast one schedule line should be due for delivery

2. There should not be a delivery block.

Please check in the sales order whether the schedule line has current or older delivery date. If the date is a future date, you cannot create the delivery.

Thanks,

Ravi

Former Member
0 Kudos

>

> Hi SAP Gurus,

>

> I am getting error message when creating delivery for an order.

> Error : No schedule lines due for delivery upto the selected date.

>

> Please advise

>

> Naveen

HI Naveen,

Goto VA03 double click the line item.

Then go to schedule lines and check the date on which confirmed quantity is available.

If confirmed quantity is not available goto MB1C or MIGO and post the move require stock into required palnt and storage locations.

If it is available make it sure that while creating The delivery VL01n you put the date on which quantity is available any date before taht would throw this error message.

Hope it helps

Regards

Abhishek