Dear Community,

I have to admit that I dont know a lot of the activity status EODL. A read about it and I understood that this status appear as a confirmation but for external activities. I have in PS, for instance, two external activities. Both have the same control key (wich is external), both have a PR, a PO and an accepted SES. BUT one activity having a CNF status and the other one having EODL + the CNF status. Both on the same network by the way!

What did I missed?