Hello Guru's,
I have currently setup time stream with planning period type as Day .
1) I wanted to understand what is purpose of planning period type in CTM time stream.
2) With the current setting when i am running i see that the a quantity of 72 planned order is spread over 2 days.How is that the planned order is spread over 2 days . Instead CTM should have generated only orders with start and end date in the same day as my planning period is days.