Diffrent Plant diffrent Lot size calculation

Hi,

I have a requirement where we Need to create production order in 3 diffrent storage Location or plant. In each Plant or storage Location i have to use 2 diffrent way to for calculation of lot size for planned order. In on storage Location it should fix lot, in second storage Location it should as per SO rquirement.

Pls let me know how to map this senario in SAP.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 19, 2016 at 04:25 PM

    Hello

    The only way to map this requirement is using storage location MRP areas and setting a different lot sizing procedure for each MRP area.

    Regards,
    Caetano