Insert Appropriate values for fiscal year and period

Hi all,

While trying to save project created using project builder (CJ20N) in the development system, error message: "Insert Appropriate values for fiscal year and period". It is a customized error message.

No error when project is saved with PD alone. Error comes when I try to save the project with root level WBS element(no network, or any other element)

Kindly suggest what needs to be done to fix this error.

Muraleedharan.R

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 06, 2008 at 04:44 PM

    Hello,

    I suspect that a validation is at work at top WBS level. It comes into play when you try to save root WBS but not when you save PD. This validation is defined in project profile for automatic validation.

    We have a similar scenario-- a check at the time of setting the top WBS to CLSD.

    Thanks,

    Sourabh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 06, 2008 at 03:26 PM

    It's a guess:

    Though there seems to be no identifiable link, the error text suggests it's got something to do with budgets.

    Try the WBS creation/save after de-activating the availability control in the budget profile.

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 08, 2008 at 03:12 AM

    Hi,

    I thank you both for the prompt reply .

    The problem has been solved when automatic validation was removed from project profile.

    Regrds

    Muraleedharan.R