Hello, colleagues.

I want that at the primary resource change for process order operation, the issuing storage location automatically changed for all components assigned to that operation.

I have PSA maintained in resource and storage location defined in PSA.

But when I change resource in COR2 or CM25 the storage location is not updated. It's either taken from the Production Version or from BOM or from Material Master.

Do you think the requested logic is possible with SAP standard?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 19, 2016 at 02:23 PM

    Hello

    The storage location should be read from the new supply area when you change the work center. However, if the storage location was not extended for the material, it will read from the production version or from the BOM.

    I suggest you to make sure that the storage location was actually extended for the component and that the deletion flag is not checked in MARD.

    You can also try to debug on LCOBOFAZ - CHECK_AFVG_FOR_LGORT.


    Regards,
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 19, 2016 at 02:09 PM
    -1

    Hello Konstanian,

    The production supply area can be used in Kanban processing and in Warehouse Management.. but it will not capture the component storage locations for Goods issue

    the storage location will be arrived from material master --> MRP2-->Production storage location to process order

    if you have not maintained that then it will be blank in the process order component overview

    the primary resource change for process order operation, the issuing storage location automatically changed for all components assigned to that operation.

    For this you have to update the storage locations manually in COR2 or while making the confirmation against phase (Operation) through COR6N

    Regards,

    Venkatesh..