on 10-19-2016 1:44 PM
Once the PO is APPROVED, the person who is creating the PO is able to change the quantity, price, date and ship to columns, and i believe the approver sees the status as PO in "progress" and the approver is helpless to stop or re-approve it.
How can we make sure that the PO once approved, if changed later has to be resend for approval. can i make some changes in the business roles to eliminate this issue. Please advise.
Hello Anees,
In order to trigger re-approval for purchase order you have to configure approval process at "Purchase order header re-approval " and "Item Level" as per screenshot :
Go to Business Configuration --> Implementation Projects --> select Project --> Edit Project Scope --> Questions --> Purchasing --> Purchase Request & Order Management --> Purchase Order --> click on checkbox for Do you want to use the header re-approval process for purchase orders?
Re-approval triggers only when you make changes to Quantity, price, Account assignment.
Best Regards,
Sahalya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |