on 03-03-2008 7:56 PM
Hi All,
I am facing an issue with MRP results.
We are having some matetrials which we plan/forecast in one plant (A) whereas procured it from another plant (B) through STO scenario. Now for one material after MRP, in plant B system has generated 3 Purchase Requisitions (each of Qty-240) correctly as per the requirement. And in plant A after MRP, system should generate 3 planned orders with reference to 3 PR's from plant B BUT the system has generated 4 Planned Order (each of Qty-240).
Now I am unable to trace the reason, hwy system has generated fourth Planned Order in plant A.
Please if anybody can help me out in this issue.
Awaiting for favourable reply.
Regards,
Anup
Hi
Can you please specify what is appearing in MD04 for that material in plant A.
Regards,
Krishna Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you maintained any safety stock setting in plant A ?
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.