Hi All,

I am facing an issue with MRP results.

We are having some matetrials which we plan/forecast in one plant (A) whereas procured it from another plant (B) through STO scenario. Now for one material after MRP, in plant B system has generated 3 Purchase Requisitions (each of Qty-240) correctly as per the requirement. And in plant A after MRP, system should generate 3 planned orders with reference to 3 PR's from plant B BUT the system has generated 4 Planned Order (each of Qty-240).

Now I am unable to trace the reason, hwy system has generated fourth Planned Order in plant A.

Please if anybody can help me out in this issue.

Awaiting for favourable reply.

Regards,

Anup

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Can you please specify what is appearing in MD04 for that material in plant A.

Regards,

Krishna Mohan

former_member184627
Active Contributor
0 Kudos

Hi,

Have you maintained any safety stock setting in plant A ?

Regards,

Senthilkumar