Advance Procurement /Long Lead item

Former Member
0 Kudos

Hi Experts,

We have some long delivery items in BOM for which we are trying advance procurement. We have maintained strategy 70, item category'L' in material master and attached the material to an activity which is 2 months prior to the scheduled production. We generated PR for this item and created PO however during the Project MRP run, system is generating PR again for this item. Please inform which are all the settings required to prevent the PR getting generated again during project MRP.

Any help on this issue is highly appreciated.

Points assured.

Best Regards

Afroz Ahmed

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check in tcode OPPQ .Select your plant. Rescheduling horizon tab, Input no of rescheduling horizon days.Ex: 100 days.Make tick mark in fixed purchase requirement.

This will solve your problem.

Regards,

Dharma

Answers (1)

Answers (1)

former_member698542
Active Contributor
0 Kudos

Hi Afroz,

Please maintain individual collective indicator in material master MRP-4 view of the long lead time material to

"2-collective. So that the system will consume the existing stock.

Thanks and regards

Murugesan