on 02-29-2008 10:24 AM
Hi friends,
Is it possible to create scheduling agreement (type Lp or LPA) with reference to contract ( type Wk.
when I am trying through me31L, I am getting error as below,
"Contr. release order only allowed for sch. agmts. w. time-dep. conditions"
can any body through some light on this how to slove this error.
Thanks
Suresh
Hi,
You can create SA wrt Contract.
Thanks
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the error is coming becoz pls follow:
spro-mmpurchasing-scheduling aggrement-define document types---here u will see that time dependent condition is checked.
pls try and create inforecord and then this error should not come.
regards,
indranil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In ME31L Select the Doc type as LP or LPA, Then click on Ref to Contract Tab..
It will allow you to create the contract..
Thx
Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For Doc Type LP and LPA in config , Time dependent conditons ( Purchase Info Records ) are mandatory. Hence this error.
You can check in SPRO-MM-Purchasing-Schedule agreement-Define Document Types ( go to the end of the Doc tpyes LP/LPA ) , Time depende column will be Tick marked.
Create an info reord and proceed.
Regards
Reward Points if useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.