Dear sap experts,
i have issue my client want to reverse the settlement document in project system.
they did in cj88
they settled with web cost element to asset .
is it possible to reverse the that settled document.
plz help me out
i will assign points if i get solved.
regards
ravi
Hello,
Yes. it can be reversed using CJ88 itself. There is an option to reverse last settlement at the top. But the period should be open. And you can reverse the just previous settlement.
Thanks,
Sourabh
Edited by: Sourabh Saxena on Feb 29, 2008 8:59 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I think you can reverse it.Go to settlement and click on reverse.
Vardhini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.