Hi

I have a project whose budget and availibility control has been changed. Is there a way I can see what changes have been made to the budget and availibility control as well as the user id?

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

You can check CJI8 for the budget line items. This will provide an overview on the different releases, returns, suppelements etc, performed over the original budget.

If status change documents are active, you can check change documents for status AVAC, ISBD, etc. This will provide an overview on the availability control changes.

Hope this helps

Regards

Martina

Answers (2)

Answers (2)

Former Member
0 Kudos

Juliet,

You can get the document number in CJI8.However, if you select the correct layout in CJI8, you will obtain all the necessary information without the need of calling CJ3B.

Regards

Martina

Former Member
0 Kudos

Thank you very much - CJI8 works beautifully!! Thank you everyone for your help.

Regards Juliet

Former Member
0 Kudos

Changes in the budget or allocation of original budget values always generate a document and you can see then using T Code CJ3B.You can also see who has created the document.

Regards

Sreenivas

Former Member
0 Kudos

Hi Sreenivas, CJ3B requires a document no. Where would I find the document no.? Iuse CJ31 to look at the budget and I have noticed a budget change. I want to see who changed it and what the value of the change was. thanks for your help. Juliet

Former Member
0 Kudos

Martina's suggested report is best fit for your requirement. Change the report layout to include the fileds budget type, created by,document number etc.,

Regards