on 02-27-2008 3:37 PM
Hello SAP PP Guru,
while reu MD04creating purchese requiest for ROH material in popup windo it shows document type as a NB but MM Guyes has define new document type as ZNB
we have make changes in T code OMDV and OPJP as replese NB with ZNB
but after this setting we runTcode MD04 but it dose not attatch document type as ZNB
can any ine tell me where we can replace or change that document tpye as ZNB
regards
puru
Puru
You maintain the Planned order profile for the new Document type in SPRO>> Production >>MRP>>Procurement Proposals>>Planned orders>> define Planned order profiles.
So based on the control parameters
Order type
Procurement type
Special procurement
Acct assignment cat.
While conversion the system will pick the Document type
BR
SK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Assign the MRP group for Raw material also. Now run the MRP for Header material and convert the planned order of ROH (if avilable ) to PR & see the document type or Direct PR for ROH.
How do u create the PR for ROH ,
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Puru,
Maintain the MRP Group for material & and Assign the document type ZNB for MRP group & now system will pick up the ZNB type for PR.
Goto OPPR -> External procurement-> schedilung/doc type-> asign the ZNB for "stnd purch ord" field.
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.