Unable to pick the milestone in invoicing Plan PS and MM Integration

Former Member
0 Kudos

Dear friends

i have created a invoicing plan type Z1. and with date category 01. I have assigned the the billing rule as " 1 Milestone billing on percentage basis" and Fixed date as 1 Planned/ Actual date from Milestone".

I have assigned the invoice plan type Z1 and date category 01 to Milestone usage also.

This invoicing plan type is assigned to network profile. I created a internal processing activity and I am assigning the Invoicing plan as Z1. I have created a line item for 10 % payment and i tried to assign dates from Milestone. But the dates are not getting assigned.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This issue was solved. In Milestone, sales document date field has to be tocked