Hello,

Can anyone tell me how I can use CS_BOM_EXPL_MAT_V2 to actually explode the BOMs and create the demand. I get the return values in the itab but I don't know what to do to create the demand/documents required to actually explode the BOM.

In this case I have a kanban that is not creating the documents required to refill an empty kanban if it uses subcontracting. How can I take the results from CS_BOM_EXPL_MAT_V2 and create the proper demands?

Thanks,

Matt

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Answer - BAPI_GOODSMVT_CREATE might work (I didn't use it) or you can use what I used...a BDC to process ME38 > Delivery Schedule > Item > Component > New BOM explosion.

Matt

Former Member
0 Kudos

How can I take the results in CS_BOM_EXPL_MAT_V2 and create the actual procurement of those components?

BAPI?