Hi Experts ,

When we create a sales order with an item of item category (TAS)(Third part sales) a purchase requisition is automatically created and these requisitions pick a G/L account which is defined for third party sales

We have been using this G/L account for third party sales and never defined this account as cost element.

We do not want to post the charges in to controlling , is this possible for us to correct the error without changing message control?

Now when we convert such purchase requisitions in to a purchase order system gives an error "define G/L account 60100071 as cost element".

Earlier we have been creating PO's from PR's with same GL account.

I am new to this module and will appreciate if can get some documentation on account determination and posting of charges at my personal email anand.troy@gmail.com

Any help in this regard will be appreciated,

Thansk & Regards

Anand Tripathi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 24, 2008 at 11:22 PM

    HI,

    One of the reasons why SAP is giving you this error message is because in case of TAS, the sales order itself becomes the CO object. You can't avoid making a posting to CO in this scenario.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Akhilesh,

      Thanks for your reply.

      what exactly determines whether it should post to a CO or not, like when it should search for CO object and when it should not.

      In our case earlier we used tocreate TAS with same G/L account and it never asked for a CO object, problem started after a hot pack was implemented.

      We ahve checked SAp note 356094 but we never defined message KI280 as error message in OBA5.

  • avatar image
    Former Member
    Jul 07, 2008 at 08:18 PM

    Nothing much helpful has been received from forum.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Anand

      do not change the message to be able to temporarily correct this error - cos this will lead to further problems later

      the reason u get this error is cos this is a scenario where the setting tells the system it is made inhouse, so it wants to cost it -

      this setting is maintained on the Material master, MRP 1 view - material group field - if u have a PTO there, usually the system things that the item is going to be produced in- house, therefore this error

      if u take this off, it should be fine

      hope this helps