Hi All,

In LTP scenario, the Sales Orders in MS04 should disappear when I do not select "Consider Sales Orders" in MS32. But it is not working in case of configurable materials. Please suggest if there is any other setting so that Sales Orders will not appear in MS04.

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Hi Caetano,

Any suggestion on how to deactivate the checkbox "Use make-to-order and project planning"? For the time being we have created a new Planning Scenario and working with that.

Thank you

0 Kudos

hi Caetano,

"Use make-to-order and project planning" is already checked. We want to deactivate it. but it is grayed out. Can you let me know how to do it.

Thank you

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Make sure that the flag "Use make-to-order and project planning" is set.

Regards,