on 02-22-2008 9:49 AM
What do we confirm during confirmation of proces order?
Hi,
With a confiramation of order we confirm or specify following
1.The quantity of material in an operation that was produced as yield, scrap and the quantity to be reworked (GR)
2. The quantity of material was used in an operation (GI)
3.How much work was actually done (Production activity )
4.Which work center was used for the operation
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Debasish,
We confirm that a particular operation/phase was processed for a qty which we are confirming and also consumed materials for that operations(Backflush).
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Transaction CORK is used for confirmation of process order.
Pl. refer,
http://help.sap.com/saphelp_46c/helpdata/en/05/603bc6462311d182b50000e829fbfe/frameset.htm
Goto Process order>Completion confirmation of process order
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.