PPDS (1709) Resource operative versión 000 not updates from Independent model

Nov 28, 2017 at 09:25 PM

44

avatar image

Hi,


I'm trying to configure a PPDS model in an S4H environment (1709 version) and I've the following issue.

When I create for the first time the Work Centers in S4H, once I save the creation, the PPDS resurce is automatically created as It's expected, not only for the independent model but also for the operative version 000.

But the following changes at the Work Center are automatically updated only at the independent model, not at 000 version.


¿How can the resource can be updated for the 00 version?


Thanks in advance.

Best Regards

ppds-resource.png (29.9 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Óscar Cases Sospedra Dec 20, 2017 at 07:29 PM
0

In customizing transaction CFC9 you must select the value N at the field Change Transfer Mode at the Resource fields group.