on 11-28-2017 9:38 AM
Hi,
Based on priorities the Required Start and End dates are selected in PM Notifications as per standard settings in SPRO. It work fine. When overdue reports is run the result is based on Required End date whci is fine too.
Sometime user want to change the Required End date so it is no more Overdue for genuine reasons like Plant was shutdown during that period etc. As field is greyed out it cannot be changed.
What could be done?
Thanks
Faisal,
Assuming that the notification in no closed, then the Required End Date (VIQMEL-LTRMN) is usually open for entry.
If, not then you have probably greyed-out this field via configuration (transaction OIAL).