SNP Heuristics Basics: Demand Propogation and Plant Planning

Nov 25, 2017 at 01:41 AM


avatar image

Hello Guru's,

Hope some one could please shed some light on heuristics planning .

I have a DC and a plant and the transportation duration is 8 days and the supply at plant and DC is Zero

When i run heuristics on DC and plant i see there is Distribution demand generated at plant is for today (Nov 24th) and the planned orders are generated for Dec 4th.

Question : I understand that the demand was first propogated from DC to plant but how is that we have an STR starting from plant on 24th when the supply (planned order generated by heuristics ) is on Dec 4th.

Does heuristics generate STR even with out supply at plant on that given day.