Hi, All
Can I use MRP Type V1 for process with T.code MD61?
How can it set?
Thank you
WA
Hello
If your question is if MRP type V1 can be used with planned independent requirements, then the answer is that this MRP type won't consider PIRs in the net requirements calculation.