Skip to Content
avatar image
Former Member

Can I use MRP Type V1 with T.code MD61?

Hi, All

Can I use MRP Type V1 for process with T.code MD61?

How can it set?

Thank you

WA

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 27, 2017 at 04:03 AM

    Hello

    If your question is if MRP type V1 can be used with planned independent requirements, then the answer is that this MRP type won't consider PIRs in the net requirements calculation.

    Regards,

    Caetano

    Add comment