Hi, All

Can I use MRP Type V1 for process with T.code MD61?

How can it set?

Thank you

WA

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Nov 27, 2017 at 04:03 AM
0

Hello

If your question is if MRP type V1 can be used with planned independent requirements, then the answer is that this MRP type won't consider PIRs in the net requirements calculation.

Regards,

Caetano