Validity Date on oppurtunity

Hi Experts -

I have requirement to determine the Oppurtunity end date based on Start date with the custom logic. but i dont see an option to do that since those dates are not visible in SDK .

Can you please help if this is possible ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Oct 20, 2016 at 02:35 AM

    Hi Prem,

    Open the UI in UI Designer and try to find the field and it's BO mapping.

    Thanks, Pradeep.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 19, 2016 at 02:52 AM

    Hi Prem,

    You could access it using

    OPPORTUNITY->SALES_FORECAST->EXPECT_PROCESSING_DATE_PERIOD->

    -START_DATE

    and

    OPPORTUNITY->SALES_FORECAST->EXPECT_PROCESSING_DATE_PERIOD-

    -END_DATE

    Thanks, Pradeep.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 19, 2016 at 08:27 PM

    Thanks Pradeep. You are awesome!

    Can you please let me know how do find out under which object a field is available. like "F1" help in SAP.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 20, 2016 at 07:24 PM

    Thanks Pradeep

    Add comment
    10|10000 characters needed characters exceeded