Former Member
Feb 20, 2008 at 03:36 AM

multiple account assignment of p.r while acct. assignment is P & itemcat-D

75 Views

I AM FACING A PROBLEM IN CREATION OF P.R HAVING MULTIPLE ACCOUNT ASSIGNMENT . I AM TAKING ACCT. ASSIGN MENT CAT- P i am distubting in different WBS ELEMENT. BUT SYSTEM GIVES AN ERROR MESSAGE

Multi acct. assgt. not allowed for ind. cust. req. or engineer-to-order

Message no. 06268

Diagnosis

Multiple account assignment is not defined for items with account assignment to "individual customer requirement" or "manufacture for individual project" (engineer-to-order).

This means that you can only enter one account assignment item in the case of individual customer requirement or engineer-to-order.