Technical completion of Plant Maintenance Order

When we are trying to do a Technical Completion of a PM order we are getting the error as Error in commitment check (see costing log) with Message no. IW079.

Unable to figure out the missing configs .... kindly help!

Thanx

Shivaji

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Feb 19, 2008 at 12:37 PM

    There might be some open commitments (PO's) against the Order for which you are trying to set this status. Check the commitment report.

    This is nothing to do with configuration as this is standard check.To reduce/cancel the commitments set "Delivery completed" indicator in the purchase order which are using this order as account assignment.

    Regards

    Sreenivas

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.