Availability Check

santosh_kanta3
Participant
0 Kudos

Hi,

i am having a problem. i am using Planning Strategy 10 i.e Make -to- Stock. when i run MRP the system should not consider the stock available. for example i am a stock of 10 nos of Material A. when i create Planned Independent Requirements using T.Code MD61 for 10 nos. during MRP run it should create Independent Requirements although for the material A stock available is 10.

Thanks,

Santosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Even with planning strategy 10, you can make the system should not considering the available stock.

Use tcode OMDX, define planning horizon no of days make it Nil.

Now run mrp, system should not consider the available stock for new requirement.

Regards,

Dharma

santosh_kanta3
Participant
0 Kudos

Hi Dharma,

Thanks for ur reply. in T.code omdx i made the planning horizon nil. then also MRP run is considering available stock. please tell me what should i do for this?

Thanks & Regards,

Santosh

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi,

Change the stock to Consignment based stock so that during MRP run it will not consider the existing stock. Please let me know wether it is working?

Murali krishna

Former Member
0 Kudos

Hi,

If u want to exclude the stock from Particular stoarge loaction during the MRP, Set at MMSC and try

Regards

Pradeep

Former Member
0 Kudos

Hi Santosh

Prerequisites

You need to maintain the following master data for the finished product:

Maintain strategy group 11 on the MRP screen.

Set the Mixed MRP indicator to 2 on the MRP screen.

Maintain the item category group (for example, NORM) on the Sales Organization

screen.

Maintain the Availability check field so that you perform an availability check without the

replenishment lead time (checking group 02 in the standard system).

Plz reward points if the info is useful to u

Former Member
0 Kudos

Hi,

In MRP 3 view Strategy group 11 and mixed MRP indicator

gross requirements planning.

Regards,

nandha

santosh_kanta3
Participant
0 Kudos

Hi Nandakumar,

Thanks for ur reply. what are the other settings to be maintained?

Regards,

Santosh

Former Member
0 Kudos

HI

Use strategy 11 instead if you dont want stock to be considered.

Regards,

Krishna Mohan

santosh_kanta3
Participant
0 Kudos

Hi Krishna,

Thanks for ur reply. what are the settings to be done for using strategy 11.

Thanks & Reply,

Santosh