Hi,

i am having a problem. i am using Planning Strategy 10 i.e Make -to- Stock. when i run MRP the system should not consider the stock available. for example i am a stock of 10 nos of Material A. when i create Planned Independent Requirements using T.Code MD61 for 10 nos. during MRP run it should create Independent Requirements although for the material A stock available is 10.

Thanks,

Santosh