on 02-18-2008 12:26 AM
Hi Gurus,
can you please tell me what is the purpose of the traffic light in the delivery due list
Thanks,
Paul
The color of the traffic light tells you whether the logistics process
regarding delivery scheduling is still in planning.
The following is valid for order schedule lines:
o Green means that there is enough time to process the delivery.
As the preliminary document for this delivery (sales order, for
example) was being processed, delivery scheduling determined a date
for delivery creation that falls more than two days later.
o Yellow means the delivery is waiting to be created.
Planned delivery creation is today or tomorrow.
o Red means this delivery is urgent and should be created soon.
The preliminary document is overdue and the planned delivery creation
date has past. The customer may not recieve this delivery on time.
The following is valid for deliveries:
o Green indicates that there is enough time to process the planned goods
issue. Delivery scheduling determined a planned deadline for goods
issue that falls more than two days later.
o Yellow means the planned goods issue is waiting to be processed. The
planned delivery creation date is today or tomorrow.
o Red means it is urgent that this goods issue be posted. The delivery
is overdue and the planned goods issue date has past. The customer may
not receive this delivery on time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The color of the traffic light tells you whether the logistics process
regarding delivery scheduling is still in planning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.