Skip to Content

Forward and backward scheduling.

Hi Experts,

I am very confused between forward and backward scheduling. Requesting you to please elaborate it with examples.

Regards

Vivek

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 27, 2017 at 04:36 PM

    Forward scheduling takes the Basic Start Date and caluclates the Basic Finish Date..

    Backwards scheduling takes the Basic Finish Date and caluclates the Basic Start Date.

    PeteA

    Add comment