Feb 16, 2008 at 11:35 AM

Schedule Line dates

16 Views

Dear PP gurus,

Our scenariao in make to stock REM. Some of the components are procured externally through Schedule lines.

We have created scheduling Agreements,

maintained purchasing info record for vendor, maintained source list.

Through MRP run sys is creating scheduling lines it is fine.

But my customers repmt is that sys should create schedul lines after 5 days of requirements date(Date of PIR of header) For this I maintened 5 days planned del time in MRP 2 view, also maintained 5 days in purchasing info record but still sys is creating schedule lines on PIR's date.

Component mrp type is PD, lot size is TB (daily lot size) no strategy group No checking in availability check.

Please guide me how to handle it.

Thanks & Regards

Dhananjay Kulkarni