Could anybody tell me the significance of Date type field under lead time in days field in Document type?
Hi,
When you create schedule lines for a sales document, you can specify different formats for the delivery date (day, week, or month). This indicator enables the system to refer to a particular format, independent of the language in which it appears on the user interface.
Regds
MM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kiran,
The relevence of DATE TYPE field is ;
Defines the date format to be used.
The date type indicates whether the delivery date is expressed as a day (date type D), a week (date type W) or a month (date type M).
regards
MBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran,
If Date type is Day Lead time in days = 5 then delivery date is Order date +5
Order date is 1st === delivery date is 6th
If Date type is Week Lead time in days = 5 then delivery date is Order date +5 Weeks
Order date is 1st === delivery date is next 4th or 5th
If Date type is Month Lead time in days = 5 then delivery date is Order date +5 Months
Order date is 1st Jan === delivery date is 1st Jun
I hope it is help full.. rewards if it Useful
Regards
Durga Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.