Skip to Content
0
Former Member
Feb 12, 2008 at 01:27 PM

Progress tracking Procedure In PS

372 Views

Hi

It's a investment Project Scenario. Can anybody please tell me the required configuration for progress tracking?

Say For example, By means of an activity I've created one PR. And i want to see the status of that activity in terms of the progress of the purchasing ........i.e whether the activity is still in the PR stage or It has been moved to RFQ stage or it is in PO stage or GR has been done for that activity or goods has been issued to the activty.........so on till the actual cost has been booked to the particular activity.

Can anyone please let me know that how such kind of progress tracking can be done so that I can see the progress in project planning board or in some project report.

Waiting for your prompt reply

With Best Regards

Som