Hi All

We transfer a materiel Multilevel BOM from ECC to GTS system.

I can only see one level BOM,

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Mouaz BEN REDJEB Nov 24, 2017 at 08:21 AM
0

Hi Farooq,

Are these recursive BOMs ?

What are the settings you have maintained in ECC in:

Sales and Distribution > Foreign Trade/Customs > SAP Global Trade Services - Plug-In > Control Data for Transfer to SAP Global Trade Services > Control Transfer of Bills of Product for Preference and Re-Export

Regards.

Mouaz BEN REDJEB

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Dec 18, 2017 at 01:38 PM
0

Mouaz BEN REDJEB Thank you for the reply ,

In the setting specified , we have 2 entries : BOM Catagory Static and configurable-> type of explosion is top-down(multi step) ,plant based preference determination, assemby and production are checked.

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Mouaz BEN REDJEB Thank you for the reply , the requirement is solved ,

When the material bom is exploding using the FM CS_BOM_EXPL_MAT_V2

the field GS_PACK_BOM_EXPLODE-PARAM-FBSTP is set to 'X'

implemented a customer exit to make GS_PACK_BOM_EXPLODE-PARAM-FBSTP = ' '.

0
Mouaz BEN REDJEB Dec 21, 2017 at 09:31 AM
0

Hi, try to change the type of explosion from top-down to bottom-up.