Hi Experts,

We are using PPM 6.1 and have a scenario where we need to schedule tasks at hour level ( in fraction of days). Is it possible to have duration of tasks in fraction of days or hours.

With Regards,

Nachiket

Accepted Solutions (0)

Answers (1)

Answers (1)

francesco_pezzoli
Active Participant
0 Kudos

Hello Nachiket,

The time unit for the duration of project elements is always "Day", there is no option to use a different unit for duration. Furthermore no decimal values are allowed.

This is a design restriction in Project Management (as documented in the online help): Scheduling

Best Regards

Francesco