You are attempting to assign activity type WAGES to the work center. Howeve

Former Member
0 Kudos

Dear all

while creating work center for the newly created plant ( master data not yet uploaded ), in costing tab while entering labour activity type , it is giving the above error. Please help me out

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184655
Active Contributor
0 Kudos

Dear GB,

1.Create a Cost centre using T code KS01.

2.Create Activity Type using T code KL01.

3.Assigning Rate's to Activity Types to Cost centre using T

code KP26.In the input screen assign the periods properly for

the Financial Year which you want to make use of.

4.Once all this settings are done,then assign the cost centre

and proper activity type where some rate has been assigned for

that activity type to that cost centre.

Otherwise while costing operation costs will not be captured

properly.

Regards

Mangalraj.S

Former Member
0 Kudos

error is

You are attempting to assign activity type WAGES to the work center. However, this activity type has not yet been set up in controlling area 5000 for cost center 906000

Former Member
0 Kudos

U need to do activity creation using KL01 for Cost centres and cost center's creation using KS01.

Assigning rates for the activity types Cost centre wise in KP26

Note that common point between activity type and cost center is controlling area....

This will resolve the issue

Rgds

Edited by: Vicky Khabrani on Feb 11, 2008 11:37 AM

Former Member
0 Kudos

First In KP26 maintain the value of activity type WAGES for the cost center 906000.After then assign this acitivity type to the work center.