Dear All

We are currently performing an EhP8 upgrade on the Development system of our ECC6 on-premise business suite. The SPDD phase was done and dictionary adjustments saved in a transport. However the assignment of the transport for modification adjustment in follow-on systems was not done, and the next upgrade phase to ACTUPD started.

Is there a way to introduce the SPDD transport at a later phase?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Ged Hurst Nov 22, 2017 at 04:10 PM
0

We resolved the problem in the following way:

1. Include transport request in umodauto.lst in abap/bin folder.

2. Place a break point aftter the phase MAIN_SHDRUN/UEXP_SPDD_SAV.
Check the logs of this phase if the transport is read correctly.

3. Save the K & R file created during this phase.

4. At post-processing if umodauto.lst in trans/bin is not updated properly. do export of transport as per note 68678.