on 02-08-2008 12:10 PM
Hi,
My customer wants to block the capacity of the particular workcentre on 25 of every month .
Pl explain how to configure this.
Regards
Thamizhchelvan
Hi,
You may create shift definition accordingly & assign it to the work centre capacity for all such days...
Configuration T-Code :OP4A
Thanks
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To do every month 25th as a block to capacity
Create a PM order with this work cenre as main work centre and make start and end date as 25th. See that in the Order screen, enter sycondition = 1 so that that day the capacity considered as not available in capacity planning table...just and come back
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.