We are upgrading our solution manager system to 7.2. In 7.1 we are using Test workbench for manual testing. For upgrade we need to close all test plans in 7.1.

Please some one let me know how to close test plans.

Step by step procedure needed. Not able to find any steps regarding this issue.

Regards,

Vijay

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Tom Cenens
Nov 21, 2017 at 09:53 AM
0

Hi Vijay

I assume they mean maintaining the status of the test plan in transaction STWB_2.

Can you have a look there please and check the status field in test plan attributes to see if you can put a status that means "closed" or "finalized" in there?

Best regards

Tom