dear sap gurus,

while creating PIR in ME11 in p.org data screen planned delivery time is not accepting by the system i am getting the following error]

make an entry in all required fields

also conditions screen is not opening

please guide me thank you

damodar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

the main reason for not accepting condition button is that you might have maintained schema group in vendor master or you can maintain your conditions in MEK1 and the error for "make an entry in all fields " is try maintaining all the required fields . check MMR, VMR and settings in the configuration.

Former Member
0 Kudos

thanks to SSP, and MANI for your immediate response

my problem is solved and thanks to all

ok bye

Former Member
0 Kudos

Check screen layout in customization for info record..

Former Member
0 Kudos

dear SSP,

i checked screen layout planned delivery time is required entry

Former Member
0 Kudos

Keep this field as a optional field in all the selection keys..

especially create keys..

Former Member
0 Kudos

dear SSP, thanks for your reply i created PIR in ME11 by making optional entry

but conditions screen is not opening please guide me

Former Member
0 Kudos

R u entering purchase organization while creating info record..

Anothe thing check pricing procedure maintained at vendor schema & pur. org. combination..

Former Member
0 Kudos

Hi,

Try open the conditions tab from the Purchasing data screen