Skip to Content

Planned order type LA start date in the past

Hi expert,

I have planned order which have start date in 2013. I use backward schedulling and I don't use "start in the past" configuration in OPPR or OPU5 .Master data is created in 2015.

Why it can be happen ?

Thanks and regards

Anita

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 27, 2017 at 04:23 AM

    Hello

    Check if start in the past is allowed in OPPQ.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded