on 11-21-2017 6:51 AM
Hi expert,
I have planned order which have start date in 2013. I use backward schedulling and I don't use "start in the past" configuration in OPPR or OPU5 .Master data is created in 2015.
Why it can be happen ?
Thanks and regards
Anita
Hello
Check if start in the past is allowed in OPPQ.
Regards,
Caetano