Hi, in my company we changed from Discrete to REM production, but we have a problem with Cost Estimate (CK11N),

We make an cost estimate in CK11N now in REM and only appear the components from Phantom assem. The machines and labour time dont appear on CK11N.

Our solutions is repeat all machines and process in last Routing. Is this normal or there are something wrong?

So, this is the CK11N, in yellow the work centers:

Only appear these work centers:

But in phantom i have these to:

So,the materials appear in CK11N but the Work Centers no.

Thks in advance, and sorry for my bad english.

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member259539
Active Participant
0 Kudos

check your rate routing i think your planned quantity is very small thats why its showing zero value.increase planned quantity in rate routing and check again. If problem remain the same then share rate routing screen shot. please also check its planned cost in kp26 as well. may be its two small thats why its showing zero value in ck11n

sapires
Explorer
0 Kudos

see attach please

former_member259539
Active Participant
0 Kudos

how many activities you are using?what i understand from your question is only machine and labour activities are not appearing in Ck11n.

i appreciate if you share complete screenshot of ck11n. just check attached screenshot as an example.

rajneesh_saxena
Active Contributor
0 Kudos

Hi

Check your quantity structure settings in costing variant, specially routing section.

Regards

Rajneesh

former_member259539
Active Participant
0 Kudos

first check quantity structure in costing variant.? if its ok then please share screenshot? does system posting any error at the time of ck11n?

sapires
Explorer
0 Kudos

Hello, thks for trying help,

i update the question with images.