on 02-06-2008 12:28 PM
Hi all
I have an assembly for which I have given 3 days as the In-house production time in the Material Master View.
I have also given the operation times in the Routing of the same material. It takes upto 3 days for the total operations but the base quantity can be anything which again cannot be fixed in the routing.
When i am converting a planned order into a production order, the start date/ finish date is calculated from the times given in the routing and not the no. of days in the in-house production time. As my production is not dependent on the lot size, i want it to take from the material master.
this can be achieved if i take out the times in the routing. but the times are necessary so as to capture the activity costs of that material.
How do i achieve this? Is this possible at all?
Regards
Chandra
You need to make the std value as fixed value - this will solve your problem
You need to change the scheduling formula in WC (this setting is done in configuration OP55)
The processing formula given in WC is (in std SAP) is SAP002...copy it and make
it as ZAP002 in OP55 and change the formula from SAP_09 / SAP_11 * SAP_02 /
SAP_08
to SAP_09
assign this formula in WC and enter the value as 3 hrs in Routing...now systemk
will schedule for any lot size the time as 3 hrs only.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I agree with that the System will not allow deleting the Scheduling flag in control key. Sorry for my over looking.
You can try in Scheduling Parameters for the Order Type ( TC: OPU3) the Scheduling Flag is to be removed. Then the system will concider only the IHP time declared in the Work Scheduling view, and will not concider the Lead times.
If the flag is in disabled field, take technical help.
Thanks & Regards
Krishna
Hi,
Unflag the check box - "Scheduling" in your control key that is used in the routing operation.
You can define your own control key by copying from the standard one in the TC: OP67.
Thanks & Regards
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.