Production order schedule dates

261 Views

Hi all

I have an assembly for which I have given 3 days as the In-house production time in the Material Master View.

I have also given the operation times in the Routing of the same material. It takes upto 3 days for the total operations but the base quantity can be anything which again cannot be fixed in the routing.

When i am converting a planned order into a production order, the start date/ finish date is calculated from the times given in the routing and not the no. of days in the in-house production time. As my production is not dependent on the lot size, i want it to take from the material master.

this can be achieved if i take out the times in the routing. but the times are necessary so as to capture the activity costs of that material.

How do i achieve this? Is this possible at all?