Hi,
in the graphical plannig board in apo ppds I would like to have a chart into which I can drag&drop orders from the resource chart.
In the R3 graphical planning board (trans cm25) it is possible to remove/deallocate planned orders from the recource chart by dragging the pl-order from the resource chart to another chart (like a worklist).
Is this possible in the APO-scheduling planning board?
it should work as follows:
the draged pl order would disappear in the resource chart as being deallocated but it will be visible in the other chart in which I drop it.
thank you in advance!
br,
Pilvi