While running MRP with respect to Project (t-code : MD51) how I can consider unrestricted stock of BOM component (without Q assignment).

If stock is not there in warehouse then I want to generate a planned order with automatic WBS assignment.

Rashmin Gadhiya

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

This is not possible in standard. If there is an account assignment to project, system will not check if there is stock at plant level.

Regards,

Caetano

Former Member
0 Kudos

Sir,

I think my exceptions are not cleared to you.

While running a MRP (MD51), I want to consider below two type of stocks.

a) stock assigned to the same WBS

b) free stock