Hi, gurus:

We've been struggling with the following issue: is it possible to complete technically just one operation within a PM order and let the other operations within the same PM order as released?

I guess it is not possible, but we are open to ideas. Has anybody faced a similar situation?

Probably, it would be feasible to use "final confirmation" and "no remaining work" in transaction IW41, but it still does not seem to be the most recommendable option in our case.

Thanks in advance.

Best regards,

J