For short supply in project

Dear all,

This is regarding the short supply of the material in Project. Now there is requirement of delivering the material from project which is in the BOM of FERT material and at third level . I have maintained the sales views of the material. I have created the short supply sales order for the same, attached to the project but i could not deliver the material through project.

If anybody has some solution please provide.

Thanks in advance,

sudhir.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 02, 2008 at 06:54 AM

    Hi,

    In order to make short of supply of materials, the delivered materials need to be assigned to project then only deliver can happen.

    But in your case the material is a part of FERT item & in the BOM. Can you elaborate your busines scenario of material procurement & delivery to enable us suggest in better way.

    Regards,

    Rakesh Pradhan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 02, 2008 at 07:18 AM

    Hi,

    Are you able to availability check and confirm the materials in sales order ?

    Is the system passing on requirement to MRP ? - Are you able to see this requirement in MD04 ?

    If not,check the requirement type / requirement class (OVZG, OVZH) and make necessary corrections to ensure transfer of requirements and availability check.

    Check whether a delivery document type to Sales order copy control is customized (VTFL)