Hi all,

I am checking capacity availability in production order.

one of the work center is overloaded.

So I am doing finite scheduling.

But the operation is not getting despatched and operation timings are not changed.

The error system showing is 'Order 100000000042 operation 0010: No remaining av. cap. available in planning period'.

Now what is this planning period ?

What should I do so that in finite scheduling operation will be despached automatically and next time when I am checking capacity availability system should not show overload for the same order.