i need a guide on how to go about capacity requirements planning from evaluating to leveling to scheduling. thanks!!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

First configure the below settings in the capacity Planning.

1) Define time units

Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF)

2) Define Capacity Category

Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category.

3) Set up Capacity Planner.

Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner

4) Define parameters

Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B)

5)Define Move time matrix.

Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN)

6) Define Setup matrix.

Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix

7)Define Control Key.

Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG)

😎 Define Shift Sequence.

Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A)

9) Define Key for performance efficiency rate.

Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU)

11) Specify Scheduling type.

Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN)

12) Set up Production scheduler group.

Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH)

13) Select Automatically.

Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF)

14) Define Scheduling parameters for Production orders.

Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3)

15) Define Reduction Strategies planned/ production orders.

Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order

16) Define Reduction Strategies for network/process orders.

Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order

17) Define Selection profile.

Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles

bear_boy
Participant
0 Kudos

then how do i do the monitoring part of capacity planning & control?

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Here is an idea on Capacity Evaluation and Capacity Levelling:

Capacity Evaluation gives the details about the present load/Orders available for the particular work centre. It gives an idea about the available capacity and the required capacity planned for the work centre. And, if you want to change the planned production order sequence or you want to change the priority by prepone or postpond a particular Production order, you will carry out Capacity Levelling inorder to maintain the workcentre and also in over load situations. This change is done using the concept of "Dispatch" to maintain the work centre engaged suitably as per your requirement.

For more detailed description, refer to the foll link:

[Capacity Evaluation and Capacity Levelling|http://help.sap.com/saphelp_47x200/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm]

Hope this helps..

-Thaila Shree