Skip to Content
avatar image
Former Member

Routes and Transit times with Global ATP

If Global ATP is used where are the transit times managed usually? in SAP or APO. Since Transit Times are in Routes in SAP. Is there any equivalent data management point in APO?

Thanks

venkat Jupudy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jan 31, 2008 at 08:09 PM

    Hi Venkat

    You can either call scheduling locally in R/3 and also in APO as part of GATP function.

    Transit times are maintained in scheduling steps( creating condition records of condition technique scheduling) for condition type TRAN.

    Route determination can be done in R/3. There is a possibility of dynamic route determination in APO but I guess it requires TP/VS and gatp functions.

    Regards

    Mohan Venkat Ramana Chunchu

    Add comment
    10|10000 characters needed characters exceeded