Define multi development source systems

Good Day;

I am trying to figure out how to define more that one source system in Solman (ChaRM). Let me explain

Regular Corrections, all development is done in DW3 Client 100. (Production Stream)

Urgent Corrections, all development is done in DW4 Client 100 . (Emergency Stream)

Training Corrections, all development is done in DW3 Client 400 (Training Stream)

Regards

Don

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2008 at 11:42 AM

    Had been re-posted

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 17, 2008 at 09:46 PM

    Hi Don,

    Did you try creating three logical components (one for each dev box) and three maintenance projects. When a change request is created the Change Manager will have to assign the correct maintenance cycle for the type of development it is. I haven't done this before, but it seems like a good approach. Let us know how it goes.

    regards,

    Jason

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 18, 2008 at 03:28 PM

    Hi,

    I have done this approach mentioned by Jason more than once. You create as many logical components as you need, each one having the different dev system and the QAS and Prod system (and also other system roles if needed, like verification or post-processing systems ).

    How is your landscape? Do you have only one Test client and one Productive client or many? That influences how to create the system/client routes.

    You have also to define if you want to have different maintenance projects or keep all logical components in the same. In my cases I had different maintenance projects. If the Production Ibase for all is the same, the system will ask you to choose which maintenance cycle to use.

    Regards,

    Raquel Cunha.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.